Project Updates

Peoples Gas // Multiple Intersections

Please be aware that a new Peoples Gas Project will be starting in the ward at the end of May 2017.

  • This project consists of 5 replace in place intersections. The intersections are as follows:
    • Carmen Ave & Kenneth Ave
    • Ainslie St. & Kenneth Ave.
    • Lawrence Ave. & Kenneth Ave.
    • Tripper Ave & Ainslie St
    • Keeler Ave & Ainslie St.

This work will just be in intersections, will not shut down any traffic. However, parking could be restricted, so please watch for and heed posted 'no parking' signs.

The work in Lawrence will be in the north curb lane so the traffic lane will remain open. Work will start to the east and work west. School should be out by the time the project gets to the Carmen and Kenneth intersection.

Thanks in advance for your patience during this project!

 

Updates for Peoples Gas // Multiple Intersections

July 16, 2017

Progress Update

Crews are currently working in the intersection of Keeler and Ainslie relocating the main. 

 

Once crews are finished with the Keeler and Ainslie intersection, they will be working west:

  • Tripp & Ainslie
  • Kenneth & Ainslie
  • Kenneth & Lawrence
  • Already completed: Carmen & Kenneth

 

The map below is where we will be upgrading low pressure services to medium pressure starting in the next couple weeks.  There are 272 services that will be upgraded in the shaded areas shown.

August 28, 2017

August 2017 Update

Peoples Gas is planning to proceed with the second phase of their gas work to install a new main and upgrade 272 gas services to customers on the highlighted map below.

 

Work is set to begin next Monday, August 28th and will go until the end of the year most likely.  Per their permit work will also be occurring Saturdays on this project in order to be able to get all paving restoration done before the asphalt plants close. 

 

Sequence of construction:

 

1)      Keeler from Argyle to Ainslie

2)      Lowell from Foster to Ainslie

3)      Kenneth and Carmen intersection

4)      Elston and Kentucky intersection

5)      Gunnison and Kenneth from Ainslie to Lawrence

6)      Kilbourn from Carmen to Ainslie

7)      Kennison

8)      Kolmar

 

September 15, 2017

Saturday Work

UPDATE: The Peoples Gas contractor, KS Energy, will be starting to work Saturdays starting this Saturday 9/9. They will be in the 4900 block of N Lowell. 
This is needed to keep ahead of the planned sewer project and also to stay on target to get paving completed before the asphalt plants close for the season.