Project Updates

Sewer Main Project: Kilpatrick

A Sewer Main Project is scheduled to start in late-June of 2018 on Kilpatrick from Hiawatha to Knox.

Get email updates on this project by entering #7166 on the site BuildingANewChicago.org.

More on the project here. (PDF)

Updates for Sewer Main Project: Kilpatrick

July 18, 2018

New Start Date

This project was originally schedule for late June of 2018, but it was delayed until after the 4th of July holiday.

The project is now scheduled to begin at the end of July 2018.

July 30, 2018

Traffic Closure Alert: Peterson

TRAFFIC CLOSURE ALERT: 

Full closure of Peterson Avenue & Kilpatrick Avenue intersection on Saturday, August 4 for main installation. Detour Eastbound Peterson Avenue to Northbound Cicero Avenue, to eastbound Devon Avenue, to Southbound Pulaski Road, and back to Eastbound Peterson Avenue. Reverse for Westbound Peterson Avenue.

 